Stena
Britannica:
A new and
giant Stena Seamasterclass vessel
| |
 |
| |
Built by Hyundai, Ulsan, South Korea for Stena RoRo,
Gothenburg, Sweden. Newbuilding 1392. Delivered January 7, 2003. |
Stena Britannica II was delivered
from Hyundai, Ulsan in South Korea to Stena RoRo on January 7, 2003.
The suffix II was dropped when the Stena Britannica built
in 2000, was re-named Finnfellow.
The new vessel is chartered by Stena Line and took up service between
Hoek van Holland and Harwich on 25 February. Despite the 900 passengers
capacity Stena Britannica is mainly concentrating on freight.
The restaurant and bar on deck 8 are primarily used for large groups
or when additional facilities are needed due to problems with the HSS
traffic and closed when not needed. Deck 8 also holds 98 cabins occupied
by truckers who normally sleep even on the day crossings. Suitable restaurant
and bar facilities, a main galley, shop and a guest service desk are
found on deck 7, the principal passenger deck.
On deck 9 is a conference centre and 112 cabins
for two persons, 34 cabins for four persons and two cabins for dis-abled.
Deck 10 is a crew only deck.
The garages are connected with the upper decks by logically coloured
stair towers on each side. Red for port side and green for starboard
side.
Freight is carried on four different decks accessed
via a stern ramp. Between the main deck and the lower deck is a fixed
ramp in the aft part of the vessel and a partly hoistable ramp in the
forward part. From main deck to upper deck is a 50 meters long tiltable
ramp and from upper deck to weather deck a hoistable ramp. The decks
have a total of 3,479 lanemeters and 120 reefer points are fitted.
Machinery
Stena Britannica is equipped with four MAN B&W 9L40/54
main engines with a total output of 25,920 kW at 550 rpm. The main engines
are connected to two Kamewa propellers via two twin input single
output Renk gearboxes. Two Hyundai shaft generators of 2,400 kW each
are fitted. The control room is situated on the upper level on the port
side forward of the main engine room and the separator room is below.
On the other side is the boiler room with two large boilers with an
output of 3,500 kg/h at seven bars.
The auxiliary engine room is divided into two
rooms by the workshop and the central ramp and located aft of the main
engine room.
Two 1,280 kW MAN B&W Holeby 8L23/30A gensets
are installed in each room. Eight compact catalytic converters (SCR)
have been installed in connection with the silencers. The equipment
is designed to reduce the NOx output by 94 per cent, from 13 to 0,8
g/kWh.
As Stena Britannica is longer than
the berths both in Hoek van Holland and Harwich have been designed for,
an excellent manoeuvrability is of outmost importance.
Therefore two Kamewa bow thrusters of 2,200
kW each, together with two Becker flap rudders have been installed.
//Robert Hermansson
Back to SSG 24, 19 December