![]() |
![]() |
|
|||||||||||||||||||||
|
|||||||||||||||||||||
|
|
A new ship with a long history
Newbuildings are always projects where patience, flexibility and
a good deal of creativity are necessary virtues. Stena Freighter
is a project where those virtues were really tested to the limit.
Six shipyards in three countries and a berth in a French port were
all involved as well as towage operations covering a couple
of thousand nautical miles before the new vessel could enter
into its new service. Although being newly delivered, Stena Freighter already
has a remarkable history. In 1998, SEC in Italy delivered the first
vessel in a series of five 2,700-lane metres ro-ro ships ordered
by Stena Ro Ro. But at that time when the Sea Centurion entered
service for the British Ministry of Defence, MOD, the shipyard had
for some time been in financial trouble. The main reason was that
SEC had for environmental reasons been denied to expand its building
site. As a consequence, the ro-ro series was planned to be built
in three sections at three different locations, a set-up that became
too complex. The first vessel was originally intended for UND, but
when the Turkish operator cancelled due to the delay, MOD which
was to take vessel number two and three in the series, stepped in
and took delivery of the first vessel. The delay was so significant
that the delivery of the Sea Centurion almost coincided in time
with the original plan for the delivery with the second vessel in
the series. Different stages of completion So, when the bankruptcy proceedings were initiated one of five
vessels had been delivered, the Sea Centurion (today sailing as
Mont Ventoux in the Mediterranean). The other four units were in
different stages of completion. Number two, with the working name
Sea Chieftain and intended for the MOD, was finished to about 50
per cent with hull works completed. Number three, built for charter
to Transmed and to be named Aronte, had been launched. The aft section
of vessel number four, also intended for Transmed were being assembled
on the slipway and steel cutting of the fifth had begun.
In 2002, Stena Ro Ro bought vessel number two from the bankruptcy
estate at an auction. Ship number three was sold to an Italian owner. Stena Ro Ro wanted to move the vessel from the shipyard site a.s.a.p.
to avoid potential disputes. The company paid swiftly and prepared
to heave anchor and to start towage to France. The mills of Italian
bureaucracy grind slowly however, and for ten days Stena Ro Ro was
in a situation where they had paid for the vessel but without a
Bill of Sale to prove their ownership. In such a situation, it takes
a strong owner to fend off banks pressing for collateral. When the Bill of Sale at last was handed over, the tug, which fare
meter had been ticking for ten unexpected days, started to pull
and the half-finished vessel was towed to a berth in Toulon, France.
Engine works commenced and several shipyards were invited to inspect
the vessel and to file tenders for the completion works. Finally, a shipyard in Slovenia was chosen and preparations started
to tow the vessel from Toulon after six months at berth. The deal,
however, fell when the shipyard couldnt deliver sufficient
financial guarantees. A Croatian sub-contractor already working
on electrical installations then provided an alternative, in which
they teamed up with the Kraljevica shipyard in Croatia, and the
towage to the Adriatic Sea could commence.
In February 2003, the equipage arrived at the Kraljevica Shipyard.
Here, plans were once more disturbed by another troubled shipyard.
Originally, the intention was to dry-dock the vessel at the Victor
Lenac shiprepair yard in Croatia. Victor Lenac however filed for
bankruptcy, and a new dry dock facility was needed. This was found
at the Arsenale Shipyard in Venice on the other side of the Adriatic
Sea. Once again, the vessel was moved under towage to a shipyard. After
inspections and hull works, the tow headed back to Kraljevica for
finishing works. The vessel had however to make acquaintance with
yet another shipyard before being put into service. Delivery dry-docking
was carried out in Trieste, Italy, but this time the vessel steamed
to the shipyard under her own power. In the end of February this year, almost six years after the original
plans, the vessel was delivered to its owner and put into service
for her charterer Stena Line on its route between Göteborg
and Travemünde. Named Stena Freighter, she replaces
the namesake legendary ro-ro vessel, which has plied these waters
since the early 80s. So what about number three in the series, the one that was bought
by an Italian owner? This was bought by Stena last autumn, and delivered
this spring after having been completed by the shipyard Marina di
Carrara, in Italy. Named Stena Carrier she has also
replaced a namesake vessel and teamed up with Stena Freighter on
the GöteborgTravemünde run. Together they have almost
doubled the capacity on the Stena Line SwedenGermany link. //Rolf P. Nilsson Latest update 18-10-2006 8:49 |
![]() |
|
![]() |
![]() |
|
All material © Scandinavian Shipping Gazette. Scandinavian Shipping Gazette | www.shipgaz.com | info@shipgaz.com | webmaster | Contact us | Cookie information |